The Cottonmount Landfill Site is located Co.Antrim, Northern Ireland.

The site is located within Cottonmount Quarry a working hard rock quarry. The landfill site receives general municipal waste from Belfast City.

WALO UK was appointed as the principal lining contractor for the site and constructed 3 landfill cells, using dense asphaltic concrete, between 2006 and 2008.

In 2008 a cell was constructed using dense asphaltic concrete as part of a composite lining system of some 17,800 m2. The lining system comprised of a 300 mm mineral attenuation layer; 200 mm sub-base material layer; 60 mm asphaltic binder layer; 80 mm dense asphaltic concrete layer and a mastic seal coat to the base, side slopes and bund areas.

The works involved the placing of asphalt by paver and winch on a 40m slope. Once the lining was completed a 300 mm thick layer of leachate drainage stone was applied to the whole area. The works were undertaken in the winter of 2008 in very difficult weather conditions.

For further information please email WALO UK LIMITED

Click here to enquire about this story 

N.B. The information contained in this entry is provided by WALO UK LIMITED, and does not necessarily reflect the views and opinions of the publisher.