Sensitive sewer restoration work in Berlin

Protection of woodland and landscaped areas was a priority when the crumbling 100-year old sewage pipes of Germany’s Federal Institute for Material Research and Testing had to be replaced in difficult terrain.

The Federal Institute for Material Research and Testing (BAM) is a government office in Berlin. The present office, and its predecessors, has been located at the ‘Unter den Eichen’ site for over 100 years. This is a large urban area between Zehlendorf and Steglitz on the B1. However, separating the many buildings on the site are landscaped lawns with extensive wooded areas.

The BAM terrain
As well as the landscaped areas, the site comprises a large number of buildings which are connected to the main sewer by combined building sewers gravity pipes.

The existing pottery gravity pipes on the BAM property are up to 110 years old. Ingrowing roots and routing of the pottery pipes over many years have led to blockages every few metres or so. The clearing out of these pipes afforded only short term benefits because the mechanical stress to the pipe caused by routing frequently led to cracks which caused further blockages. This caused severe problems in the BAM laboratories.

When confronted on site with the problems posed by pottery pipes with pushfit couplers, the Federal Building Office specified FRIAFIT sewage fittings in connection with HDPE pipes. In addition to the light weight pipe material, FRIAFIT sewage fittings interconnect HDPE pipes are leakproof and longitudinally strong as they employ FRIAFIT fusion technology. Cracks at or near the arch springing line due to ingrowing roots, or at the couplers due to static stress or flushing out of pipes no longer occur.

Four year project
The three construction stages so far comprise the installation of PEHD pipes measuring d110, d160, d225, d355 and d450 in SDR 17.6. Further pipe installations carried out by Tiefund Wasserbau GmbH/Land Brandenburg are expected to take another 3-4 years. For the connection of these pipes and the reaches on the concrete inspection chambers, to date 754 sewage couplers, 246 sewage slideon couplers and 189 sewage inspection chamber adapters from the FRIAFIT range have been installed.

Service and support
In view of how difficult it is and always has been to dig out pipe trenches in a highly wooded area, and in particular to sink these trenches in sandy terrain, the installation of the FRIAFIT sewage system went remarkably smoothly. This was due to the light material, long dimensions of the HDPE pipes, technically comprehensive, clear and easy handling of the FRIAFIT couplers, slideon couplers and inspection chamber adapters.

Friatec also provides onsite advice and service, including a training demonstration service and testlaying.


Tags



Topics


Click a keyword to see more stories on that topic, view related news, or find more related items.

Comments

You need to be logged in to make a comment. Don't have an account? Set one up right now in seconds!


© Faversham House Group Ltd 2002. edie news articles may be copied or forwarded for individual use only. No other reproduction or distribution is permitted without prior written consent.