PZ Cussons: 25% Site utility cost reduction with Carbon Desktop
PZ Cussons have used Carbon Desktop for effective monitoring and targeting. This has enabled them to reduce their total site utility cost by a massive 25%.

Close
Close
Close
Subscribe below to recieve updates direct to your inbox
- or -
Continue to contentVerco is an environmental consultancy celebrating 30 years in the business. We help companies reduce their environmental impact and save money through data driven analysis, grounded advice and real-world solutions.
Our clients include real estate investors, manufacturers, retailers and Central Government among others.
Our vision and passion is to provide the solutions for a zero carbon world. Our results-driven services and software break down the challenge of achieving net zero into manageable steps and guide clients on their journey to net zero carbon.
We are here to help you achieve zero.
Contact
Mr John Grime
Overmoor
Neston
Corsham, Wiltshire
London
SN13 9TZ
United Kingdom
www.vercoglobal.com
11 June 2019, News release from Verco
PZ Cussons have used Carbon Desktop for effective monitoring and targeting. This has enabled them to reduce their total site utility cost by a massive 25%.
PZ Cussons is a global consumer products group with brands which span the 4 categories of Personal Care and Beauty, Home Care, Food and Nutrition and Electricals.
PZ Cussons Tangerang intalled Carbon Desktop which helped them to reduce their total site utility cost by a massive 25%.
Steam reduction
After using Carbon Desktop to identify that 85% of the steam was used in the seam ejector, the site team drilled into this data to optimise this asset. They installed automatic valves, adjusted the vacuum conditions and repaired identified leaks. This resulted in a 30% reduction in site gas use which was verified in Carbon Desktop and on the site utility bills.
?Electricity reduction
Using Carbon Desktop's virtual meters, the site team identified that compressed air makes up a significant proportion of the total site electrical load. Savings could be accurately projected for a number of improvement measures, which supported the business case for this investment. Air leaks were fixed, a VSD compressor installed and compressors sequenced through a central control system. These measures achieved a 27% reduction in the electricity used by the site air compressors.