A report, the fourth yearly independent review of the environmental credentials of the Olympics, has been published by the Commission for a Sustainable London 2012.

According to the report the Olympic Delivery Association (ODA) will meet its overall target of a 50% reduction in carbon emissions.

However, only 9% of the site’s power will come from renewable energy, less than half of the original 20% planned by the ODA.

Watch Shaun McCarthy, chair of the commission, lauch the report below:

The report also praises the site-wide Combined Cooling Heat and Power (CCHP) plant, recognising the commercial and technical constraints at the time the contract was awarded and understands a fossil fuel plant was the best available option to the ODA.

The ODA declined to comment on the report with a spokeswoman pointing instead to the fact more than £1m had been invested in carbon reduction measures for housing near the site.

The report can be downloaded by clicking here.

Luke Walsh

Action inspires action. Stay ahead of the curve with sustainability and energy newsletters from edie