Set on a two-acre island bounded by the River Wey, the site of the Abbey Mill
Business Park has a long history of manufacturing and industrial use. From the
late 19th Century to the 1930s the site was a woollen mill. Subsequently, the
site and former mill were used as an engineering works.
Investigation
The nature of the ground contamination present was consistent with the former
uses of the site Elevated concentrations of arsenic, chromium, lead and nickel
were identified together with localised “hot spots” of mineral oil.
In addition, elevated concentrations of toluene extractable material (TEM),
exceeding HSE criteria, were also detected.
Groundwater analyses were undertaken on samples which were visually contaminated
with hydrocarbons. In addition, although concentrations of methane and carbon
dioxide were found in the ground no detectable gas flows were recorded from
the standpipes indicating that the volume of methane and carbon dioxide present
is insignificant.
Remediation
As a result of the ground and groundwater contamination identified on the site,
a remediation scheme was designed and a Remediation Method Statement agreed
with the Director of Housing and Health, Guildford Borough Council and the Environment
Agency, prior to commencing work.
A constraint on remediation was that site levels should remain as existing
in order to protect the existing flood plain. Thus it was not possible to provide
additional capping layers and raise site levels. The proposed method of site
remediation therefore involved part excavation and removal of selective “hot
spots” of contamination and encapsulation, using an engineering capping
layer, to existing site levels. This was considered to be the most practical
and economic solution.
Excavation
One specific area had widespread contamination of both heavy metals and petroleum
hydrocarbons. A general site strip was removed to eliminate the majority of
these contaminants which were concentrated at the site surface. The spoil arising
was classified as hazardous industrial waste and was removed from site to a
licensed disposal facility.
During these excavations the environmental engineer supervising the works observed
that localised areas of exposed ground began to generate steam vapour with heating
of the soil mass. A probe, used to identify the extent of the heating in the
soil, confirmed that an exothermic reaction was taking place in the Made Ground.
This was confined to isolated areas comprising black or dark brown fused slag
or clinker, which easily crumbles to a fine powder, and the reaction appeared
to have been triggered by exposure to moisture and oxygen in the air.
Chemical analysis of the material was carried out and it was judged not to
be an environmental risk. Notwithstanding this assessment, on the request of
the developer, Richard Cook Ltd, all Made Ground in these areas was removed
to expose natural soils. Localised areas were excavated deeper to remove petroleum
hydrocarbons, such as mineral oil found in certain trial pits.
It was initially estimated that 3,500m&3; of contaminated material would need
to be removed from the site. However, a significant proportion of this material
was left on site and placed beneath building units as general fill. As a result,
the amount removed from site was reduced to 3,000m3 thereby safeguarding against
possible migration and avoiding unnecessary road haulage through the local area.
Encapsulation
The purpose of the capping layer is to isolate the contaminated material from
future users of the site by covering it with a physical barrier of clean material
sufficient to prevent direct contact and upward transfer of the contamination
over the long-term use of the site. Where possible, and so long as it was not
contaminated, the brickwork and concrete from the demolition of the original
buildings was crushed and reused as capping material beneath hardstanding areas.
Based on the measured gas regime, no gas protection measures have been incorporated
into the development. Notwithstanding this fact, all ground floors were constructed
as suspended slabs with an underfloor ventilated void to allow dispersion of
soil gas if any should become present for whatever reason.
Validation
The on-site works were undertaken and completed under the inspection of a qualified
geo-environmental engineer from Card Geotechnics to ensure that the excavation
and encapsulation operations complied with the agreed Remediation Method Statement.
Hence, the site has been remediated and poses no risk of significant harm to
human health or ecological systems. In line with the Government’s policy of
“suitable for use approach” the site has been remediated for the planned
end-use for office and commercial development with open landscaping and associated
hardstanding.
© Faversham House Ltd 2023 edie news articles may be copied or forwarded for individual use only. No other reproduction or distribution is permitted without prior written consent.
Please login or Register to leave a comment.