The site at Cowley Peachey near Uxbridge is situated in the London Borough
of Hillingdon within the Green Belt and Colne Valley Regional Park in a unique
position at the junction of the Grand Union Canal and Slough Arm.
The work to rehabilitate the site consists of the following elements; the excavation,
filling and disposal of earthworks, the construction of a new marina basin,
the construction of a new visitor centre and sanitary station and the demolition
of an existing boathouse and the construction of a new boathouse.
Remediation strategy
The remediation strategy adopted by Nuttall involves minimising the removal
of material from the site and to this end all excavated material has been screened:
for example, concrete and brick is to be crushed for reuse and subsoils will
be used for bulk fill. All silts and subsoils have been tested extensively to
ensure their suitability and any material found to be unsuitable removed to
licensed sites. In total 90,500m3 of material, which consisted mainly of silt,
gravel and clay, was excavated.
A large 1.5 metre deep basin will accommodate 120 canal boats and its sides
will be sheet piled with a concrete capping beam. A 500mm thick clay liner and
clay leaning wall will provide an impermeable barrier for the marina basin.
Following the construction of the marina an extensive landscaping programme
will be undertaken reusing the excavated materials and the visitor centre, sanitary
station and boathouse will be constructed.
The project commenced in January 2001 and is due for completion in Spring 2002.