Sudbury in Suffolk is to benefit from a new network of sewers and surface drains,
many of which are being jacked to minimise traffic disruption.
A new main sewer is now being built to collect the offending sewage which will
now be pumped west, below the north bank of the river, to Sudbury’s STW which
has also been upgraded by Laing and Purac. Many of the existing sewers and surface
drains are brick-built and date from Victorian times. Some are still in good
condition after 100 years of service but others are in urgent need of replacement
or re-lining. Young added: “The engineering that went into these sewers
was incredible. We have some original drawings from 1901 which themselves must
have taken hours to create.”
Today pipes which would have taken weeks to build can be installed in minutes.
Where the old pipes can be saved they are being lined by Insituform and elsewhere
replaced by Barhale using 1,200mm concrete jacking pipes supplied by Stanton
Bonna Concrete and 600mm clay pipes supplied by Naylor Drainage.
Most of the drives for the new sewers have now have been completed. Barhale
has been using machinery supplied by Japanese firm Iseki to jack up to 100m
of pipe at a time. Much longer drives are possible – in Cambridge Barhale recently
completed a drive of 307m. Staging pits are first dug at intervals along the
route, with sheet piling and braces where necessary to hold back the saturated
ground. In Sudbury groundwater is in many places just one metre below the surface.
The tunnelling machine is lowered into the staging pit along with the two main
jacks, which push against anchored props rather like train buffers. As the tunnelling
machine advances, sections of pipe are lowered into place behind it and pushed
forward by the jacks which can each apply up to 750t. Young said: “Here
we have not had to use more than 225t – there is really no need to worry until
you have to apply more than 450t.”
The orientation of the tunnelling machine is constantly monitored from a control
room at the top of the staging pit and a laser is used to assess the accuracy
of progress within a few mm. The technique has a tolerance of 1-1.50 but keeping
a straight track is the key to a successful drive. In Sudbury tunnelling is
being carried out at depths of 1-4.5m, which is relatively shallow for pipejacking,
so accurate monitoring of progress is essential.
To help keep friction to a minimum, a bentonite-based lubricant mix is also
injected under pressure between the pipes and tunnel wall. The larger Stanton
Bonna pipes also have Denso seals to create a water-tight connection. Jacking
pipes are made with a steel band which increases their cost but also increases
their strength to cope with the enormous forces involved. Stanton Bonna’s managing
director Barry Cooper said: “We have been using machine-cast jacking pipes
in Britain for three years. In Europe, where the standards for square ends are
not as strict, they have been used for about 12 years.” It is essential
pipe ends are square to transfer loads down the jacked line and achieve water-tight
joints.
The surface of a machine-cast pipe is not quite as smooth as a pipe made by
the older spinning process but Cooper claims: “As long as the bentonite
mix is applied properly this should not be a problem.” As a precaution
if pipes become jammed, interjacks are installed at points along each drive
so that force can be applied to pipes nearer the drilling face. No problems
apart from an unexpected brick wall have been encountered in Sudbury and so
the interjacks have not yet been called into play.
Barhale is trying to coincide part of its work with the demolition of the Ballingdon
bridge which crosses the river south-west of the town. This will change the
route of the one-way system and should take pressure off the roads to be worked
on. Despite efforts to minimise disruption local press have dubbed the project
“Nightmare on East Street.”
Several sections of new surface water drain are still to be jacked along East
Street, one of the main shopping streets in the town. Barhale hopes to complete
the project by Christmas instead of the official February 2002 deadline.
Throughout the project Barhale and Anglian have been in discussion with the
council and providers of other services to ensure the work is completed as quickly
and safely as possible. Young said: “Can you imagine the chaos if we’d
had to open trench down to four metres? It doesn’t really bear thinking about.”
Ground settlement is being monitored at 500 points around the town and as Sudbury
is a town of significant historical interest, archaeological investigations
have been carried out. According to Anglian’s spokeswoman Sarah Rowland: “Archaeologists
have been attending all of the pit excavations, but so far they haven’t found
anything.”
Barhale is one of a number of preferred contractors on a partnering panel with
Anglian, which also includes Miller Tunnelling. Barhale’s job list includes
projects ranging from 0.5-7M in value. The contract at Sudbury is worth around
£3M to Barhale; a project recently completed in Oxford netted the company
£6M
© Faversham House Ltd 2023 edie news articles may be copied or forwarded for individual use only. No other reproduction or distribution is permitted without prior written consent.
Please login or Register to leave a comment.